Case Synopsis
The Court determined two issues:1) whether NRCP 41(e)’s provision requiring dismissal for want of prosecution applies to an action in which the parties entered into a written and signed settlement agreement before NRCP 41(e)’s five-year deadline expired; and 2) whether the district court erred in reducing the parties’ settlement agreement to judgment. Summary written by Laura Guidry.
Recommended Citation
Guidry, Laura, "Summary of The Power Co. v. Henry, 130 Nev. Adv. Op. 21" (2014). Nevada Supreme Court Summaries. 10.