Case Synopsis

The Court determined that a notice of completion’s recording date—not the date on which the notice is signed and notarized—signifies when the notice is “issued” to trigger “substantial completion” under NRS 11.2055(1)(b) for NRS Chapter 11’s construction defect statutes of repose.