Case Synopsis
The Court considered I. Cox Construction Company, LLC’s (Cox) appeal from a district court’s order releasing Cox’s mechanic’s lien. Cox challenged the district court’s finding that the lien was untimely as clearly erroneous, arguing (1) the court should not have considered the timeliness of the lien in light of parties’ failure to raise the issue in pleadings; and (2) the district court incorrectly relied on Vaughn Materials v. Meadowvale Homes to find the lien untimely.
Recommended Citation
Franklin, Katelyn M., "Summary of I. Cox Construction Co. v. CH2 Investments, 129 Nev. Adv. Op. 14" (2013). Nevada Supreme Court Summaries. 113.